It's brought forward an EVM evaluation method with critical path to hold the project progress well through comparing with BCWP and BCWS also with BCWP CP and BCWS CP in critical path at the same time.
本文提出了一种带关键路径的挣值法评价方法,在比较分析BCWP与BCWS的同时对关键路径上的BCWP与BCWS作比较,以便更准确地把握项目进度情况。
计划工作预算费用或计划工程投资额,简称BCWS(Budgeted Cost for Work Scheduled),即根据进度计划,在某一时刻应当完成的工作(或部分工作),以预算为标准所需要的资金总额,一般来说,除非合同有变更,BCWS在工程实施过程中中应保持不变。